When Virginia State University needed new student housing on an accelerated timeline, speed and coordination were critical. Magnolia Hall, a 110,000-square-foot residence hall featuring 125 units and 423 beds, was designed, permitted, and constructed in just 13 months from contract award to occupancy. Precast construction played a key role in meeting the schedule, allowing building components to be fabricated off-site while other phases of construction progressed.
Owner
Virginia State University
Architect
Niles Bolton
Contractor
S.B. Ballard
Location
Petersburg, VA
To help meet the aggressive occupancy deadline, the project incorporated 534 precast components, including brick-faced exterior panels. Off-site fabrication progressed alongside foundations, utilities, and sitework, allowing multiple phases of construction to advance simultaneously and helping maintain momentum throughout the accelerated schedule.
Construction also took place within a constrained, active campus environment, with occupied student housing nearby and limited space for material storage, deliveries, and crane operations. Careful logistics planning, coordinated deliveries, and strategic crane movements enabled precast installation to proceed efficiently while minimizing disruption to ongoing campus activities.